The intersection of Freeman Dr and Postell St showing the lack of sidewalk

Transportation

Freeman Street, Postell Street, and Coleman Street Sidewalk Project

We are installing new sidewalk!

We are installing a five-foot-wide sidewalk on Freeman Street, Postell Street, and Coleman Street.  

  • On the east side of Freeman Street from the existing sidewalk to Postell Street; 
  • On the south side of Postell Street from Freeman Street to Coleman Street; and,
  • On both sides of Coleman Street from Postell Street to the existing sidewalk.  

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Lichuan Wang, PE
lichuan.wang@raleighnc.gov 

Project Manager
Sam Brewer
sam.brewer@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The design is complete. 

Lead Department:
Engineering Services

Construction

We have combined the project with our Rawls Drive and Brighton Road projects for construction. We have concluded advertisement for bids and will begin construction this fall. 

Lead Department:
Engineering Services

Schedule

ActivityDate
Design Public MeetingSept. 8
Advertise for Construction BidsFall 2023
Start ConstructionFall 2024
Complete ProjectSpring 2025