Brighton Road construction

Transportation

Brighton Road Sidewalk Project

We are installing a new sidewalk!

The Brighton Road Sidewalk project is the product of a successful sidewalk petition the City received in the spring of 2019.

We plan to install a five-foot-wide sidewalk with a three- and-a-half-foot setback from the curb along the east side of the street from Glascock Street to N. King Charles Road and on the west side of the street from N. King Charles Road to Millbank Street.

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

Project Details

 
Type:
Sidewalks

Contact

 

Project Manager
Lichuan Wang, PE
lichuan.wang@raleighnc.gov 

Division Manager
Sylvester Percival
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation

Subscribe

 

Design

The deign is complete. 

 

Lead Department:
Engineering Services

Construction

Construction updates

March 2025

The contractors have completed work on the following streets: Freeman Street (from the existing sidewalk to Postell Street), Postell Street (from Freeman Street to Coleman Street), and the west side of Coleman Street (from Postell Street to the existing sidewalk). They plan to finish work on the east side of Coleman Street in April.

Additionally, crews have started construction on Brighton Road (from Glascock Street to North King Charles Road). They will begin working on Rawls Drive once the projects on Coleman Street and Brighton Road are completed.

We have combined the project with our Rawls Drive and Freeman/Postell/Coleman St projects for construction. 

Lead Department:
Engineering Services

Schedule

Activity Date
Summer 2024Advertise for Construction Bids
Winter 2025Start Construction 
Summer 2025Project Completion