Drainage Assistance Program

We completed construction and installed a new stormwater pipe at the intersection of Courtland Drive and Mulberry Street. This work improves the stormwater system and prevents flooding in the area.

Project Details

 
Type:
Stormwater
Budget:
$250,000
Project Lead:
Stormwater Management
Contractors:
Kimley-Horn, Inc. (Design), City of Raleigh Transportation Field Services (Construction)

Contact

 

Erik Mayr, PE
Project Manager
erik.mayr@raleighnc.gov
919-996-4077

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete.

Lead Department:
Engineering Services

Design

This phase is complete.

Lead Department:
Engineering Services

Construction

This phase is complete.

Lead Department:
Engineering Services

Complete

We completed construction on Courtland Drive. We installed a new 18-inch pipe along  Courtland Drive and tied into an existing pipe that crosses Mulberry Street.

Courtland Drive Completed Construction

Courtland Drive Completed Construction

Lead Department:
Engineering Services

Schedule

DateActivity
Spring 2024Project Design complete
Summer 2024Construction begins
Fall 2024Construction complete