Undersized stormwater pipe on Cambridge Way

Stormwater

Cambridge Woods Way Drainage Improvements

Drainage Assistance Program

We are repairing the stormwater system near Cambridge Woods Way. Properties experience flooding from the way stormwater runoff flows in this area.  Water goes: 

  • From Yarmouth Road, Chesterfield Road, and Edenburgh Road; 
  • To the intersection of Lake Boone Trail and Edenburgh Road; and, 
  • To backyards on Cambridge Woods Way. 

 

Project Details

 
Type:
Stormwater
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Erik Mayr, PE
Project Manager
erik.mayr@raleighnc.gov
919-996-4077

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

This project supports

Raleigh's Climate Plan in Action

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Design

We have finished the design plans, which will redirect stormwater flows to an upgraded stormwater system on Lake Boone Trail. This will reduce the:

  • Amount of water on the public street; and,
  • Flooding concerns at properties on Cambridge Woods Way. 

This project is being combined with the Lake Boone Trail Street and Sidewalk Project.

Next Steps

 

Permitting and bidding for construction of the project will be completed early 2025.

Lead Department:
Engineering Services

DateActivity
August 2020Project planning began
Winter 2024Project design complete
Early 2026Project construction begins
TBDProject construction complete