Summerton Drive Drainage Improvements

Stormwater

Summerton Drive Drainage Improvements

Drainage Assistance Program

This project will improve the stormwater system at a property on Summerton Drive that is currently experiencing yard and street flooding due to insufficient inlet capacity.

Project Details

 
Type:
Stormwater
Budget:
$60,000 (Construction)
Project Lead:
Stormwater Management
Contractors:
Transportation Field Services

Contact

 

Jordan Pack
Engineer
jordan.pack@raleighnc.gov
919-996-4080

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

Conceptual level planning for the stormwater improvements has been complete and discussed with the impacted homeowners.

Project Goals

The goal of this project is to address the undersized and insufficient inlet that is causing yard and street flooding at Summerton Drive properties.

Project Surveying

The City’s Transportation Field Services crews will perform surveying and inspection of the existing pipes.

Lead Department:
Engineering Services

Design

The City will extend the 30-inch drainage pipe further upstream and install an inlet and headwall to more efficiently capture the upstream flows while allowing smaller debris to pass through the system.

Lead Department:
Engineering Services

Schedule

DateActivity
Early 2024Project Planning complete
Spring 2024Internal Project Design begins
Summer 2024Internal Project Design complete
Spring 2025Construction begins
Summer 2025Construction Completed

Project Map

Summerton Project Map