paved greenway trail

Parks and Recreation

Lake Lynn West Loop Trail Project

Trail Improvements

Upcoming Public Meeting

Our team has completed the early design plans for the project, and we want to get the public's input. We have a drop-in style meeting scheduled on Tuesday, November 12  from 4 - 7 p.m., at the Lake Lynn Community Center (7921 Ray Road Raleigh, NC 27612).

The project consultant along with City staff will be available to respond to questions.

Take the Project Survey Online 

This survey seeks input on various issues regarding the Capital Area Greenway and specifically the Lake Lynn Loop Trail. The survey will be available until Nov. 30. Take the survey today. 

Project Overview

The Lake Lynn Loop Trail is located in northwest Raleigh and connects the Lake Lynn Community Center to Lynn Road. This project includes improvements to Lake Lynn Trail Loop along the west side of the loop trail which is part of the Hare Snipe Creek Trail that extends from Ray Road to Wooten Meadow Park. Improvements to include the rehabilitation of the trail including a new base, new asphalt surface, trail widening, grading and drainage enhancements, improved access to and from adjacent communities, pavement markings, and pedestrian bridge replacement.

Project Timeline: 2024-2028

Interactive map of Park Projects
List of Park Projects

Project Details

 
Type:
Parks
Budget:
$3,907,500

Upcoming Events

 

Contact

 

Raleigh Parks
Planning and Public Engagement
David Bender, Engineer
david.bender@raleighnc.gov

Engineering Services
Design and Construction
Kelly Ham, Engineering Manager
kelly.ham@raleighnc.gov
 

Lead Department:
Parks, Recreation and Cultural Resources
Participating Department:
Engineering Services
Service Unit:
Parks

Subscribe

 

Planning

No planning phase involved in this bond project.

Design

The design team has initiated the project's design phase. They are scheduled to complete the final design plans in Summer 2025.

Once the design plans are completed and the final construction plans and permits have been approved, the project will be publicly bid for construction.
 

Construction

Complete


Project Schedule

DateActivity
Summer 2025Design, Permitting, Acquisition Complete
Spring 2026Advertise for Construction
Spring 2026Estimated start of construction. Please note when we have a more specific date, this will be updated.
Summer 2027Estimated construction completion. Please note when we have a more specific date, this will be updated.