People walking on the greenway trail

Parks and Recreation

Crabtree Creek Trail Improvements at Lassiter Mill Road

Strengthening greenway connections

This project will improve a section of the Crabtree Creek greenway trail corridor between Hartford Street and Lassiter Mill Road. The project includes enhancements to the currently unpaved trail section and stream bank just west of Lassiter Mill Road; removal of the timber boardwalk and steps along Hartford Street and improvements along the Lassiter Mill Road vehicular bridge.

These improvements will help strengthen the cross-city connection of the Crabtree Creek Corridor. Cross-city Greenway Trails are identified as main routes of the Capital Area Greenway System, providing connections throughout the city and to neighboring jurisdictions. To the east, Crabtree Creek connects to the Neuse River Trail, Knightdale, Wake Forest, and Johnson County. To the west, it connects to Mine Creek Trail and Umstead State Park, with the completion of the Crabtree Creek West project. 

Project Details

 
Type:
Greenways and Trails
Budget:
$2,000,000; funding provided through CAMPO’s Locally Administered Project program
Contractors:
Prime Consultant: The John McAdams Group (Design, Permitting, Construction Administration) Sub-Consultants: Kimley-Horn & Associates and Falcon Engineering

Contact

 

Construction Project Manager
Lexi Yates
lexi.yates@raleighnc.gov

Raleigh Parks
Design Project Manager 
David Bender
david.bender@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources
Participating Department:
Engineering Services
Service Unit:
Roadway Design and Construction

Subscribe

 

Planning

The Crabtree Creek Trail Improvements at Lassiter Mill Road project is being conducted in three phases. The first phase included a survey, flood study, public engagement process, and alternative analysis. This phase was completed in the Summer of 2019.  Public involvement meetings were held from March through April 2019. The project is currently in the second phase which includes the design and permitting. This is anticipated to be completed in Early 2022. The third phase will include the construction which is estimated to be completed in Late 2023.

Design

The design team has received final environmental permits needed for this project. All final plans have been submitted to North Carolina Department of Transportation (NCDOT) and the department of environmental Quality (NCDEQ).

 

 

Next Steps

 
  • The City is waiting to received construction authorization from North Carolina Department of Transportation (NCDOT).
  • Bid project for construction contract
     

Construction

The third phase of this project includes construction administration (CA), construction engineering & inspections (CEI) and construction material testing (CMT). Estimated construction completion is anticipated for summer fall 2025. 

Complete

Phase details coming soon.


History

The City’s 2014 Parks Bond Referendum includes funding for design and construction of the Crabtree Creek Trail Improvements at Lassiter Mill Road.

Schedule

DateActivity
December 2020Open House Presentation and Public Survey
Fall 2024Design, Permitting, Acquisition Complete
Fall 2024NCDOT Construction Authorization
January 2025Advertise for Construction
Spring 2025Estimated start of construction. Please note when we have a more specific date, this will be updated.
Summer 2026Estimated construction completion. Please note when we have a more specific date, this will be updated.

Related Projects

  All projects