Battleford Drive Pipe

Stormwater

Battleford Drive Drainage Improvements

Stormwater Drainage System Improvements

Raleigh Stormwater is analyzing and designing stormwater drainage improvements near the intersection of Battleford Drive and Pine Creek Court.

Project Details

 
Type:
Stormwater
Budget:
$312,000 (Design)
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Greg Marshall
Senior Engineer
greg.marshall@raleighnc.gov
919-703-5059

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

We are planning surveys and developing design options to improve the drainage system near the intersection of Battleford Drive and Pine Creek Court. More information will be provided as the project continues.

Project Goals

  • Reduce flooding on residential properties
  • Update and improve existing stormwater pipes and infrastructure
Lead Department:
Engineering Services

Schedule

DateActivity
Winter/Spring 2024Project Planning begins
Late 2024Project Design begins
Early Spring 2026Project Design complete
Late Summer 2026Construction begins
Early Summer 2027Construction complete