Courtland Drive Construction

Stormwater Improvements


Code Yellow

Raleigh Stormwater crews will begin construction the week of September 23, 2024 to update stormwater piping on Courtland Drive.

What You Can Expect

  • We are planning for total construction to be approximately eight to ten weeks depending on weather, to be completed during the week of November 25, 2024.
  • Work hours will be Monday - Friday from 7:30 a.m. to 5:00 p.m., with no work scheduled on the weekend, except in an emergency or with prior approval from the City. You will be notified if such schedule changes need to take place.

Road Closures

We will have to close the road to through traffic during construction. Detours will be added to divert traffic around the construction area. Local residents will have access to their driveways and will be able to come and go as needed except when the pipe installation directly impacts their driveways.

Department:
Engineering Services

Subscribe