Yorkgate Drive Stormwater Improvements After Construction

Stormwater

Yorkgate Drive Stormwater Improvements

Channel Repairs

A sinkhole formed from channel scour occurring at the outlet of the concrete box culvert in the driveway of 2001 Yorkgate Drive. In addition, the concrete pad constructed on the channel banks, as part of a previous City CIP project, was undermined due to mobilization of boulders that once protected the channel bed and banks.

Stormwater Management developed a new design and completed an alternative that involved the construction of a boulder wall system on either channel bank.

Project Details

 
Type:
Stormwater
Budget:
$118,000 (construction)
Contractors:
KBS Earthworks

Contact

 

Raleigh Stormwater
raleighstormwater@raleighnc.gov
919-996-3940

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is completed.

Lead Department:
Engineering Services

Design

Stormwater Management developed a new design alternative that involved the construction of a boulder wall system on either bank for approximately 20 linear feet of channel.

Lead Department:
Engineering Services

Construction

Construction of this project began in October 2022.

Lead Department:
Engineering Services

Complete

Construction of this project has been substantially completed in January 2023.

Lead Department:
Engineering Services

Yorkgate Drive Stormwater Improvements

Schedule

Date

Activity

Fall 2021

Planning phase completed

Winter 2021

Design for project begins

Summer 2022

Design phase completed

October 2022

Construction for repairs begin

January 2023

Construction completed