Southwest Beaverdam Sewer Replacement

Improvement project will replace aging materials to meet future infrastructure capacity demand.

This is a sewer replacement project. Once complete, project will enhance our shared water system.

Project Details

 
Type:
Water and Sewer
Project Lead:
Breanne Wood, PE

Contact

 

Breanne Long, PE
Engineering Supervisor
Phone: 919-996-3732
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water
Participating Department:
Water
Service Unit:
Water Treatment

Subscribe

 

Design

This project is in the design phase. 

Lead Department:
Water

Right of Way Acquisition

Check back for further phase details. 

Lead Department:
Water

Construction

Check back for further project phase details. 

Lead Department:
Water

Complete

Check back for further project phase details.

Lead Department:
Water

History

Check back for further details

Schedule

DATE ACTIVITY
Winter 2025 Project Design Complete
Spring 2025 Permitting Complete
Spring 2025 Easement Acquisition Complete
Summer 2025 Project Bid Complete
Summer 2025 Project Construction Begins
Winter 2027 Project Construction Complete