An old stormwater pipe near a home on Melbourne Road

Stormwater

Melbourne Road Drainage Improvements

Drainage Assistance Program

We are putting in larger stormwater pipes at properties on Melbourne Road to reduce flooding during heavy rainstorms. 

Project Details

 
Type:
Stormwater
Budget:
$190,000
Project Lead:
Stormwater Management
Contractors:
Timmons Group (Design)

Contact

 

Todd Rall
Project Manager
todd.rall@raleighnc.gov
919-996-4006

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Design

Design work is completed. We are getting all the required easements for this project.

Goal 

Replace 150 feet of an 18-inch stormwater pipe with a new 48-inch pipe. Making this change will reduce flooding to two homes on Melbourne Road.

Lead Department:
Engineering Services

Construction

Phase details coming soon. 

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Lead Department:
Engineering Services

Schedule

DateActivity
February 2020Project planning began
Fall 2024Project design complete
TBDProject construction begins
TBDProject construction complete